Shore Front Parkway Labyrinth and Seating Area Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a labyrinth and seating area at Shore Front Parkway.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2018
Projected Completion Date: September 2019
Completion Date: October 2019

Procurement

Start Date: October 2019
Projected Completion Date: July 2020
Completion Date: February 2022

Construction

Start Date: June 2022
Projected Completion Date: June 2023
Completion Date: March 2023

Understand how we build parks.

Funding

Total Funding: $2,421,000
Funding Sources:
  • Borough President
  • City Council
  • Federal
  • Mayoral

Location

Rockaway Beach Boardwalk, Queens
Shore Front Parkway between Beach 92nd and Beach 94th Streets
Community Board: 14

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 10/11/2024