Shore Front Parkway Multi-Purpose Area Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a multi-purpose sports field at Shore Front Parkway.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: April 2018
Projected Completion Date: October 2019
Completion Date: December 2019

Procurement

Start Date: December 2019
Projected Completion Date: August 2020
Completion Date: March 2022

Construction

Start Date: May 2022
Projected Completion Date: May 2023
Completion Date: May 2023

Understand how we build parks.

Funding

Total Funding: $6,940,000
Funding Sources:
  • Borough President
  • Federal
  • Mayoral

Location

Rockaway Beach Boardwalk, Queens
Shore Front Parkway between Beach 81st Street and Beach 77th Street
Community Board: 14

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project