Shore Front Parkway Multi-Purpose Area Construction
-
100% complete
-
100% complete
-
100% complete
This project will construct a multi-purpose sports field at Shore Front Parkway.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: April 2018
Projected Completion Date:
October 2019
Completion Date:
December 2019
Procurement
Start Date: December 2019
Projected Completion Date:
August 2020
Completion
Date:
March 2022
Construction
Start Date: May 2022
Projected Completion Date:
May 2023
Completion Date: May 2023
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- Federal
- Mayoral
Location
Rockaway Beach Boardwalk, Queens
Shore Front Parkway between Beach 81st Street and Beach 77th Street
Community Board: 14
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 11/22/2024