Bay Breeze Park Construction
-
100% complete
-
100% complete
-
76% complete
This project will construct Bay Breeze Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: April 2018
Projected Completion Date:
October 2019
Completion Date:
April 2021
Procurement
Start Date: April 2021
Projected Completion Date:
January 2022
Completion
Date:
July 2023
Construction
Start Date: October 2023
Projected Completion Date:
October 2024
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Federal
- Mayoral
Location
Bay Breeze Park, Queens
Beach 88th Street and Beach Channel Drive
Community Board: 14
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project