Shore Front Parkway Gateway Structure Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a gateway structure at Shore Front Parkway.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: January 2018
Projected Completion Date: July 2019
Completion Date: November 2019

Procurement

Start Date: November 2019
Projected Completion Date: August 2020
Completion Date: January 2022

Construction

Start Date: January 2022
Projected Completion Date: January 2023
Completion Date: November 2022

Understand how we build parks.

Funding

Total Funding: $3,298,000
Funding Sources:
  • Borough President
  • City Council
  • Federal

Location

Rockaway Beach Boardwalk, Queens
Shore Front Parkway at Beach 94th Street
Community Board: 14

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 10/11/2024