Shore Front Parkway Dog Run Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a dog run along Shore Front Parkway.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: January 2018
Projected Completion Date: July 2019
Completion Date: August 2019

Procurement

Start Date: August 2019
Projected Completion Date: May 2020
Completion Date: August 2021

Construction

Start Date: September 2021
Projected Completion Date: September 2022
Completion Date: May 2022

Understand how we build parks.

Funding

Total Funding: $1,837,000
Funding Sources:
  • Borough President
  • Federal
  • Mayoral

Location

Rockaway Beach Boardwalk, Queens
Shore Front Parkway at Beach 90th Street
Community Board: 14

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 10/11/2024