Rockaway Community Park Reconstruction

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will reconstruct the natural areas within Rockaway Community Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: December 2018
Projected Completion Date: June 2020
Completion Date: April 2024

Procurement

Start Date: April 2024
Projected Completion Date: April 2025

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Greater than $10 million
Funding Sources:
  • Federal
  • Mayoral

Location

Rockaway Community Park, Queens
Almeda Avenue, Norton Avenue, Beach 58th Street, Sommerville Basin, Beach 49th Street, Conch Basin
Community Board: 14

 

Project Staff

Contact NYC Parks about this project

Last updated: 11/22/2024