Rockaway Community Park Reconstruction
-
100% complete
-
5% complete
-
0% complete
This project will reconstruct the natural areas within Rockaway Community Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: December 2018
Projected Completion Date:
June 2020
Completion Date:
April 2024
Procurement
Start Date: April 2024
Projected Completion Date:
April 2025
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Sources:
- Federal
- Mayoral
Location
Rockaway Community Park, Queens
Almeda Avenue, Norton Avenue, Beach 58th Street, Sommerville Basin, Beach 49th Street, Conch Basin
Community Board: 14
Project Staff
Contact NYC Parks about this projectLast updated: 11/22/2024