Astoria Park Charybdis Playground Reconstruction and Spray Shower Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Charybdis Playground and construct a spray shower in Astoria Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: May 2017
Projected Completion Date: May 2018
Completion Date: June 2018

Procurement

Start Date: June 2018
Projected Completion Date: March 2019
Completion Date: July 2019

Construction

Start Date: September 2019
Projected Completion Date: March 2021
Completion Date: July 2021

Understand how we build parks.

Funding

Total Funding: $11,561,000
Funding Sources:
  • City Council
  • Mayoral

Location

Astoria Park, Queens
Between Shore Boulevard and 19th Street at 23rd Road
Community Board: 01

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 11/22/2024