Pinehurst Avenue Step Street Garden Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct the garden at the step street at West 181st Street and Pinehurst Avenue.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: May 2018
Projected Completion Date: May 2019
Completion Date: June 2022

Procurement

Start Date: June 2022
Projected Completion Date: December 2020
Completion Date: February 2024

Construction

Start Date: April 2025
Projected Completion Date: April 2026

Understand how we build parks.

Funding

Total Funding: $649,000
Funding Sources:
  • Borough President
  • City Council
  • Mayoral

Location

West 181st Street and Pinehurst Avenue

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 11/22/2024