Staten Island Reforestation FY19

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will remove invasive species and plant new and replacement trees to mitigate wildfires in Staten Island.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2017
Projected Completion Date: March 2018
Completion Date: March 2018

Procurement

Start Date: March 2018
Projected Completion Date: November 2018
Completion Date: June 2019

Construction

Start Date: May 2019
Projected Completion Date: May 2024
Completion Date: May 2024

Understand how we build parks.

Funding

Total Funding: Less than $1 million

Location

Various locations in Staten Island

Project Staff

Contact NYC Parks about this project

Last updated: 10/11/2024