Staten Island Reforestation FY19
-
100% complete
-
100% complete
-
100% complete
This project will remove invasive species and plant new and replacement trees to mitigate wildfires in Staten Island.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: November 2017
Projected Completion Date:
March 2018
Completion Date:
March 2018
Procurement
Start Date: March 2018
Projected Completion Date:
November 2018
Completion
Date:
June 2019
Construction
Start Date: May 2019
Projected Completion Date:
May 2024
Completion Date: May 2024