Bushwick Inlet Park (50 Kent Avenue) New Park Construction
-
100% complete
-
100% complete
-
100% complete
This project will construct a portion of Bushwick Inlet Park at 50 Kent Avenue.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: June 2018
Projected Completion Date:
July 2019
Completion Date:
August 2019
Procurement
Start Date: August 2019
Projected Completion Date:
May 2020
Completion
Date:
March 2021
Construction
Start Date: April 2021
Projected Completion Date:
April 2022
Completion Date: December 2022