Bushwick Inlet Park (50 Kent Avenue) New Park Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a portion of Bushwick Inlet Park at 50 Kent Avenue.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: June 2018
Projected Completion Date: July 2019
Completion Date: August 2019

Procurement

Start Date: August 2019
Projected Completion Date: May 2020
Completion Date: March 2021

Construction

Start Date: April 2021
Projected Completion Date: April 2022
Completion Date: December 2022

Understand how we build parks.

Funding

Total Funding: $6,722,000
Funding Source: Mayoral

Location

Bushwick Inlet Park, Brooklyn
Kent Avenue between North 11th Street and North 12th Street
Community Board: 01

 

Project Staff

Project Liaison: Davey Ives