Sheepshead Bay Piers Electrical & Structural Components Reconstruction (Hurricane Sandy)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    57% complete

This project will reconstruct the electrical and structural components at Sheepshead Bay Piers.

Project Notes

Due to COVID related impacts, this project may have experienced schedule delays.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: August 2017
Projected Completion Date: August 2018
Completion Date: September 2020

Procurement

Start Date: September 2020
Projected Completion Date: June 2021
Completion Date: March 2023

Construction

Start Date: September 2023
Projected Completion Date: September 2024

Understand how we build parks.

Funding

Total Funding: $14,264,000
Funding Sources:
  • Federal
  • Mayoral

Location

Sheepshead Bay Piers, Brooklyn
Emmons Avenue between East 21st Street and East 26th Street
Community Board: 15

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 10/11/2024