Sheepshead Bay Piers Electrical & Structural Components Reconstruction (Hurricane Sandy)
-
100% complete
-
100% complete
-
76% complete
This project will reconstruct the electrical and structural components at Sheepshead Bay Piers.
Project Notes
Project Update: This project is in active construction.
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: August 2017
Projected Completion Date:
August 2018
Completion Date:
September 2020
Procurement
Start Date: September 2020
Projected Completion Date:
June 2021
Completion
Date:
March 2023
Construction
Start Date: September 2023
Projected Completion Date:
September 2024
Adjusted Completion Date: January 2025
Understand how we build parks.
Funding
Funding Sources:
- Federal
- Mayoral
Location
Sheepshead Bay Piers, Brooklyn
Emmons Avenue between East 21st Street and East 26th Street
Community Board: 15
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project