Sheepshead Bay Piers Electrical & Structural Components Reconstruction (Hurricane Sandy)
-
100% complete
-
100% complete
-
65% complete
This project will reconstruct the electrical and structural components at Sheepshead Bay Piers.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: August 2017
Projected Completion Date:
August 2018
Completion Date:
September 2020
Procurement
Start Date: September 2020
Projected Completion Date:
June 2021
Completion
Date:
March 2023
Construction
Start Date: September 2023
Projected Completion Date:
September 2024
Adjusted Completion Date: January 2025
Understand how we build parks.
Funding
Funding Sources:
- Federal
- Mayoral
Location
Sheepshead Bay Piers, Brooklyn
Emmons Avenue between East 21st Street and East 26th Street
Community Board: 15
Project Staff
Project Liaison: Davey Ives