Sheepshead Bay Piers Electrical & Structural Components Reconstruction (Hurricane Sandy)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    76% complete

This project will reconstruct the electrical and structural components at Sheepshead Bay Piers.

Project Notes

Due to COVID related impacts, this project may have experienced schedule delays.

Project Update: This project is in active construction.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: August 2017
Projected Completion Date: August 2018
Completion Date: September 2020

Procurement

Start Date: September 2020
Projected Completion Date: June 2021
Completion Date: March 2023

Construction

Start Date: September 2023
Projected Completion Date: September 2024
Adjusted Completion Date: January 2025

Understand how we build parks.

Funding

Total Funding: $14,264,000
Funding Sources:
  • Federal
  • Mayoral

Location

Sheepshead Bay Piers, Brooklyn
Emmons Avenue between East 21st Street and East 26th Street
Community Board: 15

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 02/21/2025