Flushing Meadows Corona Park Aquatic Center Partial Reconstruction
-
0% complete
-
0% complete
-
0% complete
This project will partially reconstruct the Flushing Meadows Corona Park Aquatic Center.
Project Notes
Project Update: A meeting was held with stakeholders to discuss the scope of work for the project. Parks is now reviewing feedback from the meeting and the scope of work to determine the schedule for the project.
Project Timeline
Design
Assigned & Start Date: February 2022
Projected Completion Date:
August 2023
Procurement
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Flushing Meadows Corona Park, Queens
131-04 Meridian Road
Community Board: 03, 04, 06, 07, 08
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 11/22/2024