Franz Sigel Park Ballfields and Basketball Court Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct two natural turf ballfields and a basketball court in Franz Sigel Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2018
Projected Completion Date:
October 2019
Completion Date:
May 2021
Procurement
Start Date: May 2021
Projected Completion Date:
January 2022
Completion
Date:
August 2023
Construction
Start Date: July 2023
Projected Completion Date:
July 2024
Completion Date: May 2024
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Location
Franz Sigel Park, Bronx
Walton Avenue, Grand Concourse, East 158th Street, East 151st Street
Community Board: 04
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project
Last updated: 01/17/2025