Franz Sigel Park Ballfields and Basketball Court Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct two natural turf ballfields and a basketball court in Franz Sigel Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2018
Projected Completion Date: October 2019
Completion Date: May 2021

Procurement

Start Date: May 2021
Projected Completion Date: January 2022
Completion Date: August 2023

Construction

Start Date: July 2023
Projected Completion Date: July 2024
Completion Date: May 2024

Understand how we build parks.

Funding

Total Funding: $9,500,000
Funding Sources:
  • City Council
  • Mayoral

Location

Franz Sigel Park, Bronx
Walton Avenue, Grand Concourse, East 158th Street, East 151st Street
Community Board: 04

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 01/17/2025