Fox Playground Public Restroom Building Construction
-
100% complete
-
100% complete
-
100% complete
This project will construct a public restroom building in Fox Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: November 2017
Projected Completion Date:
November 2018
Completion Date:
December 2018
Procurement
Start Date: December 2018
Projected Completion Date:
September 2019
Completion
Date:
April 2021
Construction
Start Date: June 2021
Projected Completion Date:
December 2022
Completion Date: December 2022