Police Officer Edward Byrne Park Public Restroom Building Construction

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will construct a public restroom building in Police Officer Edward Byrne Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2018
Projected Completion Date: March 2019
Completion Date: November 2022

Procurement

Start Date: November 2022
Projected Completion Date: January 2020
Adjusted Completion Date: August 2024

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Source: Borough President

Location

Police Officer Edward Byrne Park, Queens
North Conduit Avenue, 130th Place, 135th Avenue, 130th Place, 134th Street
Community Board: 10

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 10/11/2024