Betsy Head Park Multi-Purpose Play Area Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will construct a new skate park, basketball courts, fitness area and multi-purpose space in the northern parcel of Betsy Head Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: November 2016
Projected Completion Date:
January 2018
Completion Date:
February 2018
Procurement
Start Date: February 2018
Projected Completion Date:
November 2018
Completion
Date:
December 2018
Construction
Start Date: December 2018
Projected Completion Date:
December 2019
Completion Date: June 2020
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Betsy Head Park, Brooklyn
Blake Avenue between Thomas S. Boyland Street and Bristol Street
Community Board: 16
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 01/17/2025