Betsy Head Park Multi-Purpose Play Area Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a new skate park, basketball courts, fitness area and multi-purpose space in the northern parcel of Betsy Head Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2016
Projected Completion Date: January 2018
Completion Date: February 2018

Procurement

Start Date: February 2018
Projected Completion Date: November 2018
Completion Date: December 2018

Construction

Start Date: December 2018
Projected Completion Date: December 2019
Completion Date: June 2020

Understand how we build parks.

Funding

Total Funding: $5,825,000
Funding Source: Mayoral

Location

Betsy Head Park, Brooklyn
Blake Avenue between Thomas S. Boyland Street and Bristol Street
Community Board: 16

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 01/17/2025