  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the perimeter fence at LaGuardia Corner Garden.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: April 2018
Projected Completion Date: April 2019
Completion Date: December 2018

Procurement

Start Date: December 2018
Projected Completion Date: September 2019
Completion Date: August 2019

Construction

Start Date: September 2019
Projected Completion Date: March 2020
Completion Date: January 2020

Understand how we build parks.

Funding

Total Funding: $379,000
Funding Sources:
  • City Council
  • Mayoral

Location

LaGuardia Place between Bleecker Street and West Houston Street

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project