Bartlett Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Bartlett Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2017
Projected Completion Date: October 2018
Completion Date: December 2018

Procurement

Start Date: December 2018
Projected Completion Date: September 2019
Completion Date: April 2020

Construction

Start Date: October 2020
Projected Completion Date: April 2022
Completion Date: July 2022

Understand how we build parks.

Funding

Total Funding: $6,174,000
Funding Source: Mayoral

Location

Bartlett Playground, Brooklyn
Bartlett Street and Whipple Street between Throop Avenue and Harrison Avenue
Community Board: 01

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 10/11/2024