Bartlett Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct Bartlett Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2017
Projected Completion Date:
October 2018
Completion Date:
December 2018
Procurement
Start Date: December 2018
Projected Completion Date:
September 2019
Completion
Date:
April 2020
Construction
Start Date: October 2020
Projected Completion Date:
April 2022
Completion Date: July 2022
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Bartlett Playground, Brooklyn
Bartlett Street and Whipple Street between Throop Avenue and Harrison Avenue
Community Board: 01
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 01/17/2025