Washington Park Dog Run Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    95% complete

This project will reconstruct the dog run in Washington Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2017
Projected Completion Date: November 2018
Completion Date: September 2021

Procurement

Start Date: September 2021
Projected Completion Date: April 2021
Completion Date: July 2023

Construction

Start Date: November 2023
Projected Completion Date: November 2024

Understand how we build parks.

Funding

Total Funding: $654,000
Funding Sources:
  • Borough President
  • City Council
  • Mayoral

Location

Washington Skate Park, Brooklyn
4th Avenue between 3rd Street and 5th Street
Community Board: 06

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 10/11/2024