Bushwick Inlet Park Motiva Parcel Remediation and Passive Seating Area Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    82% complete

This project will construct a new passive seating area in Bushwick Inlet Park.

Project Notes

Project Update: This project is in active construction.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: January 2019
Projected Completion Date: July 2020
Completion Date: January 2023

Procurement

Start Date: January 2023
Projected Completion Date: October 2023
Completion Date: April 2024

Construction

Start Date: March 2024
Projected Completion Date: September 2025

Understand how we build parks.

Funding

Total Funding: $9,818,000
Funding Source: Mayoral

Location

Bushwick Inlet Park, Brooklyn
Franklin Street, Kent Avenue, East River, Quay Street
Community Board: 01

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 01/17/2025