Bushwick Inlet Park Motiva Parcel Remediation and Passive Seating Area Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    68% complete

This project will construct a new passive seating area in Bushwick Inlet Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: January 2019
Projected Completion Date: July 2020
Completion Date: January 2023

Procurement

Start Date: January 2023
Projected Completion Date: October 2023
Completion Date: April 2024

Construction

Start Date: March 2024
Projected Completion Date: September 2025

Understand how we build parks.

Funding

Total Funding: $9,818,000
Funding Source: Mayoral

Location

Bushwick Inlet Park, Brooklyn
Franklin Street, Kent Avenue, East River, Quay Street
Community Board: 01

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 11/22/2024