Kelly Park Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct and expand the playground in Kelly Park, including play equipment, spray shower, swings, seating areas, benches, security lighting, fencing, drainage and water supply, electrical service, and plantings.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: November 2019
Projected Completion Date:
November 2020
Completion Date:
May 2021
Procurement
Start Date: May 2021
Projected Completion Date:
January 2022
Completion
Date:
November 2022
Construction
Start Date: February 2023
Projected Completion Date:
April 2024
Completion Date: August 2024
Understand how we build parks.
Funding
Funding Sources:
- Mayoral
- State
Location
Kelly Park Playground, Brooklyn
Avenue S between East 14th Street and East 15th Street
Community Board: 15
Project Staff
Project Liaison: Davey Ives