Kelly Park Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct and expand the playground in Kelly Park, including play equipment, spray shower, swings, seating areas, benches, security lighting, fencing, drainage and water supply, electrical service, and plantings.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2019
Projected Completion Date: November 2020
Completion Date: May 2021

Procurement

Start Date: May 2021
Projected Completion Date: January 2022
Completion Date: November 2022

Construction

Start Date: February 2023
Projected Completion Date: April 2024
Completion Date: August 2024

Understand how we build parks.

Funding

Total Funding: $13,108,000
Funding Sources:
  • Mayoral
  • State

Location

Kelly Park Playground, Brooklyn
Avenue S between East 14th Street and East 15th Street
Community Board: 15

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 11/22/2024