Scarangella Park Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct the playground in Scarangella Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: February 2021
Projected Completion Date: February 2022
Completion Date: March 2022

Procurement

Start Date: March 2022
Projected Completion Date: November 2022
Completion Date: November 2024

Construction

Start Date: November 2024
Projected Completion Date: November 2025

Understand how we build parks.

Funding

Total Funding: $6,499,000
Funding Sources:
  • Borough President
  • City Council

Location

Police Officer John G. Scarangella Park, Brooklyn
Avenue V between Stillwell Avenue and West 13th Street
Community Board: 13

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 11/22/2024