Ten Eyck Plaza Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Ten Eyck Plaza, including the play equipment and safety surfacing, a new spray shower, and a new sitting area.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2019
Projected Completion Date: March 2020
Completion Date: July 2020

Procurement

Start Date: July 2020
Projected Completion Date: April 2021
Completion Date: April 2022

Construction

Start Date: April 2022
Projected Completion Date: April 2023
Completion Date: December 2022

Understand how we build parks.

Funding

Total Funding: $1,700,000
Funding Source: City Council

Location

Ten Eyck Plaza, Brooklyn
Ten Eyck Street, Stagg Street, Lorimer Street, Union Avenue
Community Board: 01

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 01/17/2025