Randall's Island Emergency Utility Transformer Systems Reconstruction
-
100% complete
-
100% complete
-
100% complete
This emergency project will reconstruct the utility transformer systems at Randall's Island.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2017
Projected Completion Date:
April 2018
Completion Date:
July 2018
Procurement
Start Date: July 2018
Projected Completion Date:
April 2019
Completion
Date:
November 2018
Construction
Start Date: September 2018
Projected Completion Date:
January 2019
Completion Date: January 2019
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Randall's Island Park, Manhattan
Near Icahn Stadium
Community Board: 11
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 11/22/2024