Randall's Island Emergency Utility Transformer Systems Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This emergency project will reconstruct the utility transformer systems at Randall's Island.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2017
Projected Completion Date: April 2018
Completion Date: July 2018

Procurement

Start Date: July 2018
Projected Completion Date: April 2019
Completion Date: November 2018

Construction

Start Date: September 2018
Projected Completion Date: January 2019
Completion Date: January 2019

Understand how we build parks.

Funding

Total Funding: $773,000
Funding Source: Mayoral

Location

Randall's Island Park, Manhattan
Near Icahn Stadium
Community Board: 11

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 11/22/2024