Starr Playground Play Area and Spray Shower Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the playground and spray shower at Starr Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: September 2019
Projected Completion Date:
September 2020
Completion Date:
October 2020
Procurement
Start Date: October 2020
Projected Completion Date:
July 2021
Completion
Date:
August 2022
Construction
Start Date: October 2022
Projected Completion Date:
October 2023
Completion Date: August 2023
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Location
Starr Playground, Queens
Onderdonk Avenue between Starr Street and Willoughby Avenue
Community Board: 05
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 11/22/2024