Gateway Estates Phase II Park Construction
-
100% complete
-
100% complete
-
100% complete
This project will construct a new park, including a multi-purpose synthetic turf field, skate park, basketball courts, adult fitness equipment, and seating areas at Gateway Estates.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: June 2018
Projected Completion Date:
May 2020
Completion Date:
November 2020
Procurement
Start Date: November 2020
Projected Completion Date:
August 2021
Completion
Date:
June 2022
Construction
Start Date: October 2022
Projected Completion Date:
December 2023
Completion Date: September 2023
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Park, Brooklyn
Vandalia Avenue, Schroeders Avenue, Walker Street, Ashford Street
Community Board: 05
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 11/22/2024