Astoria Park Track and Field Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the track and field in Astoria Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2016
Projected Completion Date: December 2017
Completion Date: December 2017

Procurement

Start Date: December 2017
Projected Completion Date: September 2018
Completion Date: September 2018

Construction

Start Date: November 2018
Projected Completion Date: May 2020
Completion Date: October 2019

Understand how we build parks.

Funding

Total Funding: $12,854,000
Funding Sources:
  • Borough President
  • City Council
  • Mayoral

Location

Astoria Park, Queens
Shore Boulevard, RFK Bridge, 18th Street, Astoria Park South
Community Board: 01

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 01/17/2025