St. Mary's Park Plaza, Pathways, and Gil Scott-Heron Amphitheater Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the plaza, pathways, lighting, and Gil Scott-Heron Amphitheater at St. Mary’s Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: July 2017
Projected Completion Date:
July 2018
Completion Date:
August 2018
Procurement
Start Date: August 2018
Projected Completion Date:
April 2019
Completion
Date:
July 2019
Construction
Start Date: September 2019
Projected Completion Date:
September 2021
Completion Date: December 2022
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
St. Mary's Park, Bronx
St. Anns Avenue between East 143rd Street and East 149th Street
Community Board: 01
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project
Last updated: 11/22/2024