St. Mary's Park Plaza, Pathways, and Gil Scott-Heron Amphitheater Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the plaza, pathways, lighting, and Gil Scott-Heron Amphitheater at St. Mary’s Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: July 2017
Projected Completion Date: July 2018
Completion Date: August 2018

Procurement

Start Date: August 2018
Projected Completion Date: April 2019
Completion Date: July 2019

Construction

Start Date: September 2019
Projected Completion Date: September 2021
Completion Date: December 2022

Understand how we build parks.

Funding

Total Funding: $17,097,000
Funding Source: Mayoral

Location

St. Mary's Park, Bronx
St. Anns Avenue between East 143rd Street and East 149th Street
Community Board: 01

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project