Maria Hernandez Park Synthetic Turf Field Construction
-
100% complete
-
100% complete
-
100% complete
This project will construct a new synthetic turf field and adult fitness at Maria Hernandez Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2017
Projected Completion Date:
October 2018
Completion Date:
October 2018
Procurement
Start Date: October 2018
Projected Completion Date:
July 2019
Completion
Date:
April 2021
Construction
Start Date: August 2021
Projected Completion Date:
August 2022
Completion Date: June 2022