Highland Park Pedestrian Paths and Sidewalks Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the sidewalk and improve pedestrian access along a portion of Highland Boulevard.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2017
Projected Completion Date: November 2018
Completion Date: November 2018

Procurement

Start Date: November 2018
Projected Completion Date: August 2019
Completion Date: November 2019

Construction

Start Date: September 2020
Projected Completion Date: September 2021
Completion Date: August 2021

Understand how we build parks.

Funding

Total Funding: $942,000
Funding Source: Mayoral

Location

Highland Park, Queens
Highland Boulevard between Jamaica Avenue and Vermont Place
Community Board: 05, 05

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 11/22/2024