Staten Island Basketball Court Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the basketball courts, paths, fencing, landscape and park amenities at Wolfe's Pond Park, Old Town Playground, and Midland Field.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2017
Projected Completion Date: September 2018
Completion Date: September 2018

Procurement

Start Date: September 2018
Projected Completion Date: June 2019
Completion Date: September 2019

Construction

Start Date: October 2019
Projected Completion Date: April 2021
Completion Date: July 2021

Understand how we build parks.

Funding

Total Funding: $2,464,000
Funding Sources:
  • Borough President
  • City Council
  • Mayoral

Locations

  • Midland Field, Staten Island
    Midland, Mason, Bedford Avenues & Laconia Avenues
    Community Board: 02
  • Old Town Playground, Staten Island
    Parkinson Avenue, Kramer Street
    Community Board: 02
  • Wolfe's Pond Park, Staten Island
    Cornelia, Holton & Luten Avenues on Raritan Bay
    Community Board: 03
 