Seton Park Adult Fitness Area and Skate Park Construction
-
100% complete
-
100% complete
-
92% complete
This project will construct an adult fitness area and a skate park at Seton Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: November 2020
Projected Completion Date:
November 2021
Completion Date:
March 2022
Procurement
Start Date: March 2022
Projected Completion Date:
November 2022
Completion
Date:
June 2023
Construction
Start Date: September 2023
Projected Completion Date:
September 2024
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
- Mayoral
- State
Location
Seton Park, Bronx
Between Palisade and Independence Avenues and West 232nd and West 235th Streets
Community Board: 08
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project
Last updated: 11/22/2024