Julio Carballo Fields Lighting and Scoreboard Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct sports lighting and a scoreboard at Julio Carballo Fields.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: January 2019
Projected Completion Date: January 2020
Completion Date: February 2020

Procurement

Start Date: February 2020
Projected Completion Date: November 2020
Completion Date: March 2022

Construction

Start Date: May 2022
Projected Completion Date: May 2023
Completion Date: April 2023

Understand how we build parks.

Funding

Total Funding: $1,986,000
Funding Sources:
  • City Council
  • Mayoral

Location

Julio Carballo Fields, Bronx
Manida Street between Spofford Avenue and Lafayette Avenue
Community Board: 02

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project