Classic Playground Fitness Equipment Construction
-
100% complete
-
100% complete
-
100% complete
This project will construct adult fitness equipment at Classic Playground in Van Cortlandt Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2020
Projected Completion Date:
October 2021
Completion Date:
November 2021
Procurement
Start Date: November 2021
Projected Completion Date:
August 2022
Completion
Date:
April 2023
Construction
Start Date: July 2023
Projected Completion Date:
July 2024
Completion Date: June 2024
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
Location
Van Cortlandt Park, Bronx
Van Cortlandt Park South between Orloff Avenue and Hillman Avenue
Community Board: 07, 08, 12
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project
Last updated: 11/22/2024