Flushing Meadows Corona Park Adult Fitness Equipment Installation

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will install adult fitness equipment in Flushing Meadows Corona Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: April 2018
Projected Completion Date: April 2019
Completion Date: August 2020

Procurement

Start Date: August 2020
Projected Completion Date: May 2021
Completion Date: March 2022

Construction

Start Date: April 2022
Projected Completion Date: January 2023
Completion Date: July 2022

Understand how we build parks.

Funding

Total Funding: $345,000
Funding Sources:
  • City Council
  • Mayoral

Location

Flushing Meadows Corona Park, Queens
Corona Avenue and 111th Street, next to Playground for All Children
Community Board: 03, 04, 06, 07, 08

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 10/11/2024