Manuel Plaza - New Open Space Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

The project will construct a new open space at the DEP site on East 4th Street between Bowery and Lafayette Street.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2018
Projected Completion Date: October 2019
Completion Date: October 2019

Procurement

Start Date: October 2019
Projected Completion Date: July 2020
Completion Date: October 2021

Construction

Start Date: November 2021
Projected Completion Date: October 2022
Completion Date: May 2022

Understand how we build parks.

Funding

Total Funding: $1,314,000
Funding Sources:
  • Borough President
  • City Council
  • Mayoral

Location

Bowery & East 4th Street

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 10/11/2024