Citywide Reforestation FY18

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will remove invasive species and plant new and replacement trees citywide.

Project Timeline

Design

Assigned & Start Date: August 2017
Projected Completion Date: December 2017
Completion Date: January 2018

Procurement

Start Date: January 2018
Projected Completion Date: October 2018
Completion Date: September 2018

Construction

Start Date: September 2018
Projected Completion Date: September 2019
Completion Date: September 2019

Understand how we build parks.

Funding

Total Funding: $924,000
Funding Source: Mayoral

Location

Various locations citywide

Project Staff

Contact NYC Parks about this project

Last updated: 11/22/2024