Surf Playground Synthetic Turf Field Construction and Basketball Courts Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the asphalt multi-purpose play area and sport courts at Surf Playground with new basketball courts, seating area, synthetic turf and plantings.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: November 2017
Projected Completion Date:
November 2018
Completion Date:
December 2018
Procurement
Start Date: December 2018
Projected Completion Date:
September 2019
Completion
Date:
December 2019
Construction
Start Date: September 2020
Projected Completion Date:
September 2021
Completion Date: November 2021
Understand how we build parks.
Funding
Funding Source: City Council
Location
Surf Playground, Brooklyn
Surf Avenue between West 25th Street and 27th Street
Community Board: 13
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 01/17/2025