Surf Playground Synthetic Turf Field Construction and Basketball Courts Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the asphalt multi-purpose play area and sport courts at Surf Playground with new basketball courts, seating area, synthetic turf and plantings.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2017
Projected Completion Date: November 2018
Completion Date: December 2018

Procurement

Start Date: December 2018
Projected Completion Date: September 2019
Completion Date: December 2019

Construction

Start Date: September 2020
Projected Completion Date: September 2021
Completion Date: November 2021

Understand how we build parks.

Funding

Total Funding: $3,146,000
Funding Source: City Council

Location

Surf Playground, Brooklyn
Surf Avenue between West 25th Street and 27th Street
Community Board: 13

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 10/11/2024