Commodore Barry Park Ballfields Reconstruction and Track and Sports Lighting Construction

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will reconstruct the natural turf ballfields and construct new sports lighting and a track around the ballfields in Commodore Barry Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2018
Projected Completion Date: November 2019
Completion Date: April 2022

Procurement

Start Date: April 2022
Projected Completion Date: January 2023
Adjusted Completion Date: March 2025

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Greater than $10 million
Funding Sources:
  • Borough President
  • City Council
  • Mayoral
  • State

Location

Commodore Barry Park, Brooklyn
Park Avenue between Navy Street and North Elliot Place
Community Board: 02

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 10/11/2024