St. John's Recreation Center Adult Fitness Area Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct an outdoor adult fitness area at St. John's Recreation Center.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: April 2018
Projected Completion Date: April 2019
Completion Date: September 2020

Procurement

Start Date: September 2020
Projected Completion Date: May 2021
Completion Date: September 2021

Construction

Start Date: March 2022
Projected Completion Date: March 2023
Completion Date: August 2022

Understand how we build parks.

Funding

Total Funding: $354,000
Funding Source: City Council

Location

St. John's Park, Brooklyn
Prospect Place and Schenectady Avenue
Community Board: 08

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 10/11/2024