Penn Triangle Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct Penn Triangle.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: November 2017
Projected Completion Date:
November 2018
Completion Date:
November 2018
Procurement
Start Date: November 2018
Projected Completion Date:
August 2019
Completion
Date:
October 2019
Construction
Start Date: November 2019
Projected Completion Date:
November 2020
Completion Date: December 2020
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Penn Triangle, Brooklyn
Penn Street, Wythe Avenue, Williamsburg Street East
Community Board: 01
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project