Underbridge Dog Run and Forest Park Overlook Dog Run Fencing Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the fencing at Underbridge Dog Run and Forest Park Overlook Dog Run.

Project Timeline

Design

Assigned & Start Date: October 2017
Projected Completion Date: October 2018
Completion Date: October 2018

Procurement

Start Date: October 2018
Projected Completion Date: July 2019
Completion Date: June 2019

Construction

Start Date: November 2019
Projected Completion Date: November 2020
Completion Date: October 2020

Understand how we build parks.

Funding

Total Funding: $727,000
Funding Source: City Council

Locations

  • Forest Park, Queens
    Park Lane (to East & South) to (West) Metropolitan Avenue
    Community Board: 05, 05, 06, 09
  • Underbridge Dog Run, Queens
    West of Grand Central Parkway, 112 Street between 64 Avenue & 64 Road
    Community Board: 06
 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 10/11/2024