Northern Playground Synthetic Turf Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the existing multi-use synthetic turf field at Northern Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: May 2018
Projected Completion Date:
May 2019
Completion Date:
May 2019
Procurement
Start Date: May 2019
Projected Completion Date:
February 2020
Completion
Date:
February 2021
Construction
Start Date: February 2021
Projected Completion Date:
February 2022
Completion Date: September 2021
Understand how we build parks.
Funding
Funding Source: City Council
Location
Northern Playground, Queens
Northern Boulevard between 93rd Street and 94th Street
Community Board: 03
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 01/17/2025