Sunset Park Handball Court Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the handball court in Sunset Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: June 2018
Projected Completion Date: June 2019
Completion Date: June 2019

Procurement

Start Date: June 2019
Projected Completion Date: March 2020
Completion Date: April 2021

Construction

Start Date: May 2021
Projected Completion Date: May 2022
Completion Date: August 2022

Understand how we build parks.

Funding

Total Funding: $500,000
Funding Source: City Council

Location

Sunset Park, Brooklyn
44th Street, 41st Street, Fifth Avenue, Seventh Avenue
Community Board: 07

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project