Booker T. Washington Playground Synthetic Turf Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the synthetic turf field, basketball backstops, and chain link fencing at Booker T. Washington Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: April 2018
Projected Completion Date:
March 2019
Completion Date:
December 2018
Procurement
Start Date: December 2018
Projected Completion Date:
September 2019
Completion
Date:
December 2019
Construction
Start Date: September 2020
Projected Completion Date:
September 2021
Completion Date: September 2021
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Location
Booker T. Washington Playground, Manhattan
West 107th Street, West 108th Street, Amsterdam Avenue, Columbus Avenue
Community Board: 07
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 01/17/2025