Harold Ickes Playground BMX Bike & Skate Park and Multipurpose Play Area Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a BMX bike, skate park and multipurpose play area at Harold Ickes Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2017
Projected Completion Date: November 2018
Completion Date: June 2019

Procurement

Start Date: June 2019
Projected Completion Date: March 2020
Completion Date: October 2022

Construction

Start Date: March 2023
Projected Completion Date: March 2024
Completion Date: January 2024

Understand how we build parks.

Funding

Total Funding: $4,344,000
Funding Sources:
  • Borough President
  • City Council
  • Mayoral

Location

Harold Ickes Playground, Brooklyn
Hamilton Avenue between Van Brunt Street and Woodhull Street
Community Board: 06

 