Harold Ickes Playground BMX Bike & Skate Park and Multipurpose Play Area Construction
-
100% complete
-
100% complete
-
100% complete
This project will construct a BMX bike, skate park and multipurpose play area at Harold Ickes Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: November 2017
Projected Completion Date:
November 2018
Completion Date:
June 2019
Procurement
Start Date: June 2019
Projected Completion Date:
March 2020
Completion
Date:
October 2022
Construction
Start Date: March 2023
Projected Completion Date:
March 2024
Completion Date: January 2024
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
- Mayoral
Location
Harold Ickes Playground, Brooklyn
Hamilton Avenue between Van Brunt Street and Woodhull Street
Community Board: 06
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 11/22/2024