Lewis Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    74% complete

This project will reconstruct Lewis Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2017
Projected Completion Date: October 2018
Completion Date: May 2022

Procurement

Start Date: May 2022
Projected Completion Date: May 2021
Completion Date: December 2023

Construction

Start Date: January 2024
Projected Completion Date: January 2025

Understand how we build parks.

Funding

Total Funding: $1,517,000
Funding Source: Mayoral

Location

Lewis Playground, Brooklyn
Willoughby Avenue between Lewis Avenue and Marcus Garvey Boulevard
Community Board: 03

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 11/22/2024