Lewis Playground Reconstruction
-
100% complete
-
100% complete
-
74% complete
This project will reconstruct Lewis Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2017
Projected Completion Date:
October 2018
Completion Date:
May 2022
Procurement
Start Date: May 2022
Projected Completion Date:
May 2021
Completion
Date:
December 2023
Construction
Start Date: January 2024
Projected Completion Date:
January 2025