Project Timeline
Design
Assigned & Start Date: May 2018
Projected Completion Date:
May 2019
Completion Date:
June 2019
Procurement
Start Date: June 2019
Projected Completion Date:
February 2020
Completion
Date:
April 2021
Construction
Start Date: May 2021
Projected Completion Date:
May 2022
Completion Date: June 2022
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Location
Mellett Playground, Brooklyn
Avenue V between East 13th Street and East 14th Street
Community Board: 15
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 01/17/2025