Project Timeline
Design
Assigned & Start Date: September 2017
Projected Completion Date:
September 2018
Completion Date:
September 2018
Procurement
Start Date: September 2018
Projected Completion Date:
June 2019
Completion
Date:
June 2019
Construction
Start Date: September 2020
Projected Completion Date:
September 2021
Completion Date: September 2021
Understand how we build parks.
Funding
Funding Source: City Council