Vanderbilt Motor Parkway Reconstruction Phase 1

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Vanderbilt Motor Parkway from Winchester Boulevard to Springfield Boulevard.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2017
Projected Completion Date: September 2018
Completion Date: October 2018

Procurement

Start Date: October 2018
Projected Completion Date: July 2019
Completion Date: November 2019

Construction

Start Date: September 2020
Projected Completion Date: September 2021
Completion Date: September 2021

Understand how we build parks.

Funding

Total Funding: $1,946,000
Funding Sources:
  • City Council
  • Mayoral

Location

Motor Parkway from Winchester Boulevard to Springfield Boulevard

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 10/11/2024